Installation of deck of the Strawbale Pavilion, 2001


May 7:
the first step was
to install the deckposts
[note temporary scaffolding
under Chesapeake Bay window]


May 11:
12 ft posts were put in using
posthole digger + concrete mix
[to see detail of leveling
press here]

May 16:
Harry installed
supports for Delaware
Bay window + built a
miniporch at side door

May 20:
Greg & Ben
positioned the
difficult cornerpost


some other views:
May 20 May 23a May 23b

and Greg completed the
first horizontal supports


BLO fecit 20010915 refecit 20010917 - - continue to next page